5               Dolphin monitoring (Line-transect Vessel Surveys)

 

5.1               The baseline dolphin monitoring was carried out under Chinese White Dolphin (CWD) Service Contract No. HY/2011/02 for a period of three months prior to the commencement of works and agreed with AFCD.

 

5.2               The baseline line-transect vessel surveys for dolphin monitoring were conducted in September, October and November 2011 as shown in Table 5.1 and the location of dolphin transect survey is shown in Figure 4.

 

Table 5.1       Date of Baseline Dolphin Monitoring

No.

Date

Location

1

05/09/2011

W LANTAU + NW LANTAU

2

07/09/2011

NW LANTAU + NE LANTAU

3

16/09/2011

NW LANTAU + NE LANTAU

4

23/09/2011

W LANTAU + NW LANTAU

5

06/10/2011

NE LANTAU + NW LANTAU

6

10/10/2011

NW LANTAU + NE LANTAU

7

13/10/2011

NE LANTAU

8

17/10/2011

W LANTAU + NW LANTAU

9

28/10/2011

NW LANTAU + W LANTAU

10

01/11/2011

NW LANTAU + NE LANTAU

11

02/11/2011

W LANTAU + NW LANTAU

12

05/11/2011

NW LANTAU + NE LANTAU

13

06/11/2011

NE LANTAU

14

07/11/2011

NW LANTAU + W LANTAU

* NW Lantau = Northwest Lantau Survey Area, NE Lantau = Northeast Lantau Survey Area, W Lantau = West Lantau

5.3               In total, 112 groups of Chinese White Dolphins, numbering 413 individuals, were observed during the three-month survey within all survey areas. Most were sighted in the West Lantau (WL) and Northwest Lantau (NWL) regions.

 

5.4               Considering the West Lantau area only, which is the survey area of concern under this Contract, the numbers of dolphin sighted during the baseline monitoring period were 49 dolphins (14 groups) in September 2011, 45 dolphins (12 groups) in October 2011, and 73 dolphins (20 groups) in November 2011.

 

5.5               Major findings along and near the future alignments of HKLR and TM-CLKL as well as the reclamation site of HKBCF (collectively called “the Site” below) are summarized as follows:

·       Dolphins were sighted but not in high concentration near the Site. The number of dolphins sighted near the site: three groups sighted near HKBCF, nine groups sighted near HKLR and one group near TMCLKL (Figure 2 & 3 of Appendix G)

·       Number of dolphin groups with large aggregation: one group near HKBCF, one group near TMCLKL and five groups near HKLR (Figure 5 of Appendix G)

·       Grids with moderate to high dolphin density near site: one grid near HKBCF, two grids along TMCLKL and and two grids along HKLR (Figure 6-7 of Appendix G)

·       Number of mother-calf pairs near alignments of HKLR and TMCLKL: one pair near HKBCF, and three pairs near HKLR (Figure 8 of Appendix G)

·       Number of feeding activities sighted along and near the site: two groups near HKBCF, and one group along HKLR (Figure 9 of Appendix G)

·       Two fishing boat-associated sightings were made near the Site (Figure 9 of Appendix G)

 

5.6               Through photo-identification work, 96 individuals were identified from 182 sightings. Some were sighted over three times during the three-month survey, indicating their frequent use of Hong Kong waters. Many of them were year-round residents and some were accompanied by calves. Ranging pattern developed showed that most of the dolphins ranged across the three survey areas including the proposed HZMB work areas.

Action and Limit Level

 

5.7               The Action and Limit levels for dolphin monitoring which are summarized in Table 5.2.

 

Table 5.2        Action and Limit Levels for Dolphin Impact Monitoring

 

West Lantau

Action Level

STG < 60% of baseline & ANI < 60% of baseline

Limit Level

STG < 45% of baseline & ANI < 45% of baseline

Remarks:

1.            STG means quarterly encounter rate of number of dolphin sightings.

2.            ANI means quarterly encounter rate of total number of dolphins.

 

5.8               The calculated Action and Limit levels are shown in Table 5.3.

 

Table 5.3        Calculated Action and Limit Levels for Dolphin Impact Monitoring

 

West Lantau

Action Level

STG < 9.86 & ANI < 36.30

Limit Level

STG < 7.40 & ANI < 27.23

 

Remarks:

1.            STG means quarterly encounter rate of number of dolphin sightings.

2.            ANI means quarterly encounter rate of total number of dolphins.

3.            Baseline value: 16.44 for ER(STG) and 60.50 for ER(ANI)

 

Event and Action Plan

 

5.9               Further monitoring should be conducted during the construction and post-construction phase to identify any potential impact caused by the HZMB project. The event and action plan for dolphin monitoring is presented in Table 5.4.

Table 5.4        Event/Action Plan for Dolphin Monitoring

 

Event

ET Leader

IEC

ER / SOR     

Contractor

Action Level

1.    Repeat statistical data analysis to confirm findings.

2.    Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences.

3.    Identify source(s) of impact.

4.    Inform the IEC, ER/SOR and Contractor,

5.    Check monitoring data.

6.    Review to ensure all the dolphin protective measure are fully and properly implemented and advise on additional measures if necessary.

 

1.    Check monitoring data submitted by ET and Contractor.

2.    Discuss monitoring results and findings with the ET and the Contractor.

1.    Discuss monitoring data with the IEC and any other measures proposed by the ET.

2.    If ER/SOR is satisfied with the proposal of any other measures, ER/SOR to signify the agreement in writing on the measures to be implemented.

1.   Inform the ER/SOR and confirm notification of the non-compliance in writing.

2.   Discuss with the ET and the IEC to propose measures to the IEC and the ER/SOR.

3.   Implement the agreed measures.

 

Event

ET Leader

IEC

ER / SOR              

Contractor

Limit Level

1.    Repeat statistical data analysis to confirm findings.

2.    Review all available and relevant data, including raw data and statistical analysis results of other parameters covered in the EM&A, to ascertain if differences are as a result of natural variation or previously observed seasonal differences.

3.    Identify source(s) of impact.

4.    Inform the IEC, ER/SOR and Contractor of findings,

5.    Check monitoring data.

6.    Repeat reviewing to ensure all the dolphin protective measure are fully and properly implemented and advise on additional measures if necessary.

7.    If the ET proves that the source of impact is caused by any of the construction activity by the works contract, the ET to arrange a meeting to discuss with IEC, ER/SOR and Contractor for necessity of additional dolphin monitoring, and/or any other potential mitigation measures (eg, consider to modify the perimeter silt curtain or consider to control/temporarily stop relevant construction activities…etc), and submit to the IEC a proposal of additional dolphin monitoring and/or mitigation measures where necessary.

 

1.    Check monitoring data submitted by ET and Contractor;

2.    Discuss monitoring results and findings with the ET and the Contractor;

3.    Attend the meeting to discuss with ET, ER/SOR and Contractor the necessity of additional dolphin monitoring and other potential mitigation measures.

4.    Review proposals for additional monitoring and any other mitigation measures submitted by ET and Contractor, and advise ER/SOR of the results and findings accordingly.

5.    Supervise / Audit the implementation of additional monitoring and/or any other mitigation measures, and advise ER/SOR of the results and findings accordingly.

1.    Attend the meeting to discuss with ET, IEC and Contractor the necessity of additional dolphin monitoring and any other potential mitigation measures.

2.    If ER/SOR is satisfied with proposals for additional dolphin monitoring and/or any other mitigation measures submitted by the ET and Contractor and verified by the IEC, ER/SOR to signify the agreement in writing on such proposals and any other mitigation measures.

3.    Supervise the implementation of additional monitoring and/or any other mitigation measures.

 

 

1.    Inform the ER/SOR and confirm notification of the non-compliance in writing;

2.    Attend the meeting to discuss with ET, IEC and ER/SOR the necessity of additional dolphin monitoring and any other potential mitigation measures.

3.    Jointly submit with ET to IEC a proposal of additional dolphin monitoring and/or any other mitigation measures when necessary.

4.    Implement the agreed additional dolphin monitoring and/or any other mitigation measures.

 

5.10           Detailed findings were reported in the Baseline Monitoring Report for Baseline Chinese White Dolphin Monitoring for Hong Kong-Zhuhai-Macao Bridge Hong Kong Projects submitted by Hong Kong Cetacean Research Project under Contract No. HY/2011/02 and can be referred to Appendix G.