Table 6.2 Event/Action
Plan for Underwater Noise Monitoring
Event |
Action |
|||
ET Leader |
IEC |
ER |
Contractor |
|
Action level triggered |
1. Inform the IEC, ER and Contractor; 2. Advise Contractor of dolphin protection
zone coverage. 3. Continue to monitor underwater noise
level. |
1.
Check
monitoring data submitted by ET. |
1. Inform Contractor. |
1.
Review the piling sequence or method; 2.
Implement the mitigation measure to
lower the underwater noise level to below action limit within 30 minutes; 3.
Implement protection zone. 4.
Closely liaise
with the ET on the progress. |
Limit level triggered |
1.
Instruct the Contractor to stop construction
work; 2.
Inform the IEC and ER; 3.
Discuss with IEC, ER and Contractor on noise
reduction proposal; 4.
Assess effectiveness of Contractor’s proposal
and keep IEC and ER informed. |
1.
Check
monitoring data submitted by ET. 2.
Discuss
amongst ER, ET and Contractor on the potential remedial actions. |
1.
Review
the proposal by Contractor; 2.
Make
agreement on the measures to be implemented. |
1. Stop construction work 2. Inform the ER 3. Review the piling
sequence or method in order to reduce the underwater noise levels to no
higher than 170 dB. 4. Submit noise reduction
proposal to the ER for endorsement. 5. Implement the agreed
measures. 6. Re-submit proposals if
problem still not under control; 7. Stop the relevant
portion of works as determined by the ER until the exceedance
is abated |