1        INTRODUCTION

 

CHEC (China Harbour Engineering Company Limited, hereafter CHEC) are the Main Contractor to responsible for the execution of the construction works for the Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Vehicle Clearance Plazas and Ancillary Buildings and Facilities under Highways Department Contract number HY/2013/03.

 

The works mainly include the construction of vehicle clearance plazas, ancillary buildings and facilities, vehicular bridges, at-grade roads, drainage, sewerage, water supplies, landscape, utilities and electrical and mechanical works, etc. for Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities.

 

The main scope of works under the Contract does not include marine construction or vessel operation related to construction works.

 

Under the clause 2.7 of Specific Condition of Environmental Permit No. VEP-463/2015, a Spill Response Plan should be submitted at least 1 month before the commencement of construction of the project.  The plan includes the actions to be taken in the event of accidental spillage of oil or other hazardous chemicals aiming to minimize the adverse effects to marine ecology. 

 

The site areas of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Vehicle Clearance Plazas and Ancillary Buildings and Facilities are located at the northeast of the Chek Lap Kok. The layout illustrated the location of the site area; please refer to the Appendix A for reference.