2    SITE CHARACTERISTICS

 

The site areas of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Vehicle Clearance Plazas and Ancillary Buildings and Facilities are located at the northeast of the Chek Lap Kok. The layout illustrated the location of the site area; please refer to the Figure 1 for reference.

 

Construction of water outfall of box culvert will be conducted at the northern-east edge of HKBCF. Silt curtains shall be installed during construction of water outfall.  No night-time marine construction will be conducted and the tentative schedule shown in Table 1 below:

 

Table 1 – Tentative Schedule for Box Culvert B Construction

Periods

Duration

Activities

End of March

1 week

Excavation

Early April

2 to 3 weeks

H-Piles Installation

Mid of April

1 to 2 weeks

Precast Installation

End of April

1 week

Backfilling & Reinstatement