The site areas of Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities – Vehicle Clearance Plazas and Ancillary Buildings and Facilities are located at the northeast of the Chek Lap Kok. The layout illustrated the location of the site area; please refer to the Figure 1 for reference.
Construction of water outfall of box culvert will be conducted at the northern-east edge of HKBCF. Silt curtains shall be installed during construction of water outfall. No night-time marine construction will be conducted and the tentative schedule shown in Table 1 below:
Table 1 – Tentative Schedule for Box Culvert B Construction
Periods |
Duration |
Activities |
End of March |
1 week |
Excavation |
Early April |
2 to 3 weeks |
H-Piles Installation |
Mid of April |
1 to 2 weeks |
Precast Installation |
End of April |
1 week |
Backfilling & Reinstatement |