Contract No. HY/2013/12 Tuen Mun – Chek Lap Kok Link – Northern Connection Toll Plaza and Associated Works
Monitoring Date: 4th March 2016
Item | Environmental Protection Measures | Location/ Timing | Implementation Agent | Status | Remarks | |||
---|---|---|---|---|---|---|---|---|
A | UA | IR | NA | |||||
1 | Existing trees on boundary of the Project Area shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at Tree Removal Application stage) | All areas / During construction | Design Consultant/ Contractor | | √ | Trees were not properly protected. Strings tied on trunks & construction materials adjacent to the trees should be remove. | ||
2 | Trees unavoidably affected by the works shall be transplanted where practical. Trees will be transplanted straight to their final receptor site and not held in a temporary nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme | All areas / During construction | Design Consultant/ Contractor | √ | Tree Transplanting Specification has been specified in P.S., no transplantation works has been carried out at this stage. | |||
3 | Hillside and roadside screen planting to proposed roads, associated structures and slope works | All areas / During construction | Design Consultant/ Contractor | √ | Construction of roads not commenced yet | |||
4 | Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone) | All areas / During construction | Design Consultant/ Contractor | √ | ||||
5 | Screening of construction works by hoardings around works area in visually unobtrusive colours, to screen works | All areas / During construction | Design Consultant/ Contractor | √ | For some area, erection of hoarding was not feasible due to |
Page 1/2
04-03-2016 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
04-03-2016 |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
04-03-2016 |
---|
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting. |
04-03-2016 |
Item 7. Ensure no run-off into water body. |
![]() |
26-06-2015 |
Item 9. Recycle of felled trees as facilities to reuse. |
Contract No. HY/2013/12 Tuen Mun – Chek Lap Kok Link – Northern Connection Toll Plaza and Associated Works
Monitoring Date: 11th March 2016
Item | Environmental Protection Measures | Location/ Timing | Implementation Agent | Status | Remarks | |||
---|---|---|---|---|---|---|---|---|
A | UA | IR | NA | |||||
1 | Existing trees on boundary of the Project Area shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at Tree Removal Application stage) | All areas / During construction | Design Consultant/ Contractor | | √ | Trees were not properly protected. Strings tied on trunks & construction materials adjacent to the trees should be remove. | ||
2 | Trees unavoidably affected by the works shall be transplanted where practical. Trees will be transplanted straight to their final receptor site and not held in a temporary nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme | All areas / During construction | Design Consultant/ Contractor | √ | Tree Transplanting Specification has been specified in P.S., no transplantation works has been carried out at this stage. | |||
3 | Hillside and roadside screen planting to proposed roads, associated structures and slope works | All areas / During construction | Design Consultant/ Contractor | √ | Construction of roads not commenced yet | |||
4 | Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone) | All areas / During construction | Design Consultant/ Contractor | √ | ||||
5 | Screening of construction works by hoardings around works area in visually unobtrusive colours, to screen works | All areas / During construction | Design Consultant/ Contractor | √ | For some area, erection of hoarding was not feasible due to |
Page 1/2
11-03-2016 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
11-03-2016 |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
11-03-2016 |
---|
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting. |
11-03-2016 |
Item 7. Ensure no run-off into water body. |
![]() |
26-06-2015 |
Item 9. Recycle of felled trees as facilities to reuse. |
Contract No. HY/2013/12 Tuen Mun – Chek Lap Kok Link – Northern Connection Toll Plaza and Associated Works
Monitoring Date: 18th March 2016
Item | Environmental Protection Measures | Location/ Timing | Implementation Agent | Status | Remarks | |||
---|---|---|---|---|---|---|---|---|
A | UA | IR | NA | |||||
1 | Existing trees on boundary of the Project Area shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at Tree Removal Application stage) | All areas / During construction | Design Consultant/ Contractor | | √ | Trees were not properly protected. Strings tied on trunks & construction materials adjacent to the trees should be remove. | ||
2 | Trees unavoidably affected by the works shall be transplanted where practical. Trees will be transplanted straight to their final receptor site and not held in a temporary nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme | All areas / During construction | Design Consultant/ Contractor | √ | Tree Transplanting Specification has been specified in P.S., no transplantation works has been carried out at this stage. | |||
3 | Hillside and roadside screen planting to proposed roads, associated structures and slope works | All areas / During construction | Design Consultant/ Contractor | √ | Construction of roads not commenced yet | |||
4 | Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone) | All areas / During construction | Design Consultant/ Contractor | √ | ||||
5 | Screening of construction works by hoardings around works area in visually unobtrusive colours, to screen works | All areas / During construction | Design Consultant/ Contractor | √ | For some area, erection of hoarding was not feasible due to |
Page 1/2
18-03-2016 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
18-03-2016 |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
18-03-2016 |
---|
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting. |
18-03-2016 |
Item 7. Ensure no run-off into water body. |
![]() |
26-06-2015 |
Item 9. Recycle of felled trees as facilities to reuse. |
Contract No. HY/2013/12 Tuen Mun – Chek Lap Kok Link – Northern Connection Toll Plaza and Associated Works
Monitoring Date: 25th March 2016
Item | Environmental Protection Measures | Location/ Timing | Implementation Agent | Status | Remarks | |||
---|---|---|---|---|---|---|---|---|
A | UA | IR | NA | |||||
1 | Existing trees on boundary of the Project Area shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at Tree Removal Application stage) | All areas / During construction | Design Consultant/ Contractor | | √ | Trees were not properly protected. Strings tied on trunks & construction materials adjacent to the trees should be remove. | ||
2 | Trees unavoidably affected by the works shall be transplanted where practical. Trees will be transplanted straight to their final receptor site and not held in a temporary nursery. A detailed Tree Transplanting Specification shall be provided in the Contract Specification. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme | All areas / During construction | Design Consultant/ Contractor | √ | Tree Transplanting Specification has been specified in P.S., no transplantation works has been carried out at this stage. | |||
3 | Hillside and roadside screen planting to proposed roads, associated structures and slope works | All areas / During construction | Design Consultant/ Contractor | √ | Construction of roads not commenced yet | |||
4 | Hydroseeding or sheeting of soil stockpiles with visually unobtrusive material (in earth tone) | All areas / During construction | Design Consultant/ Contractor | √ | ||||
5 | Screening of construction works by hoardings around works area in visually unobtrusive colours, to screen works | All areas / During construction | Design Consultant/ Contractor | √ | For some area, erection of hoarding was not feasible due to |
Page 1/2
25-03-2016 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
25-03-2016 |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
25-03-2016 |
---|
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting. |
25-03-2016 |
Item 7. Ensure no run-off into water body. |
![]() |
26-06-2015 |
Item 9. Recycle of felled trees as facilities to reuse. |