Annotation: During 1 September to 31 December 2015, major construction activity was construction of retaining wall F and the specified works included excavation, rock breaking, blinding, formworking, steel-fixing and concreting. The weather condition varied from sunny to rainy. The monitoring data was provided by the Contractor followed to their QA/QC control. |
AUES
14th Monthly Environmental Monitoring and Audit (EM&A) Report –December 2015 Contract No. HY/2013/12 – Tuen Mun -Chek Lap Kok Link -Northern Connection Toll Plaza and Associated Works
AUES
14th Monthly Environmental Monitoring and Audit (EM&A) Report –December 2015
![]() |
---|
Annotation: During 1 September to 31 December 2015, major construction activity was construction of retaining wall B and the specified works included excavation, rock breaking, blinding, formworking, steel-fixing and concreting. The weather condition varied from sunny to rainy. The monitoring data was provided by the Contractor followed to their QA/QC control. |