Contract
No. HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road
Section between Scenic Hill and Hong Kong Boundary Crossing Facilities
Monthly EM&A Report No.148 (January 2025)
13 February 2025
Revision 1
Main
Contractor Designer
Contents
Executive Summary
1.4 Construction Works Undertaken During the Reporting Month
2....... Air
Quality Monitoring
2.4 Monitoring Parameters, Frequency and Duration
2.6 Monitoring Schedule for the Reporting Month
3.4 Monitoring Parameters, Frequency and Duration
3.6 Monitoring Schedule for the Reporting Month
4....... Water Quality Monitoring
4.3 Monitoring Parameters, Frequency and Duration
4.6 Monitoring Schedule for the Reporting Month
6....... Environmental
Site Inspection and Audit
6.2 Advice on the Solid and Liquid Waste Management Status
6.3 Environmental Licenses and Permits
6.4 Implementation Status of Environmental Mitigation Measures
6.5 Summary of Exceedances of the Environmental Quality Performance
Limit
6.6 Summary of Complaints, Notification of Summons and Successful
Prosecution
7.1 Construction Programme for the Coming Months
7.2 Environmental Monitoring Schedule for the Coming Month
Figures
Figure 1.1 Location of the
Site
Figure 2.1 Environmental
Monitoring Stations
Figure 2.2 Transect Line Layout in
Northwest and Northeast Lantau Survey Areas
Appendices
Appendix A Environmental
Management Structure
Appendix B Construction Programme
Appendix C Calibration
Certificates
Appendix D Monitoring Schedule
Appendix E Monitoring Data and
Graphical Plots
Appendix F Event and Action Plan
Appendix G Wind Data
Appendix H Dolphin Monitoring
Results
Appendix I Waste Flow
Table
Appendix J Cumulative
Statistics on Complaints
Appendix K Environmental Licenses
and Permits
Appendix L Implementation
Schedule of Environmental Mitigation Measures
Appendix M Record of ¡§Notification of
Summons and Prosecutions¡¨
Appendix N Location of Works Areas
Executive Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The
main works of the Contract include land tunnel at Scenic Hill, tunnel underneath
Airport Road and Airport Express Line, reclamation and tunnel to the east coast
of the Airport Island, at-grade road connecting to the HKBCF and highway works
of the HKBCF within the Airport Island and in the vicinity of the HKLR
reclamation. The Contract is part
of the HKLR Project and HKBCF Project, these projects are considered to be
¡§Designated Projects¡¨, under Schedule 2 of the Environmental Impact Assessment
(EIA) Ordinance (Cap 499) and Environmental Impact Assessment (EIA) Reports
(Register No. AEIAR-144/2009 and AEIAR-145/2009) were prepared for the
Project. The current Environmental
Permit (EP) EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on
22 December 2014 and 11 April 2016, respectively. These documents are available
through the EIA Ordinance Register. The construction phase of Contract was
commenced on 17 October 2012.
BMT Hong Kong Limited was
appointed by the Contractor to implement the Environmental Monitoring &
Audit (EM&A) programme for the Contract in accordance with the Updated
EM&A Manual for HKLR (Version 1.0) and provided environmental team services
to the Contract until 31 July 2020.
ANewR
Consulting Limited has been employed by HyD as the
Independent Environmental Checker (IEC) and Environmental Project Offer (ENPO)
for the Project with effective from 1 October 2022.
This is the 148th
Monthly EM&A report for the Contract which summarises the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 31 January 2025.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of the monitoring activities during this
reporting month is listed below:
1-hr TSP
Monitoring at AMS5 |
3, 9, 15, 20, 24
and 28 January 2025 |
1-hr TSP
Monitoring at AMS6 |
3, 9, 15, 20, 24
and 28 January 2025 |
24-hr TSP
Monitoring at AMS5 |
2, 8, 14, 17, 23 and 27 January 2025 |
24-hr TSP
Monitoring at AMS6 |
2, 8, 14, 17, 23 and 27 January 2025 |
Noise
Monitoring |
9, 15, 20 and
28 January 2025 |
Water Quality
Monitoring |
1, 3, 6, 8,
10, 13, 15, 17, 20, 22, 24 and 27 January 2025 |
Chinese White
Dolphin Monitoring |
2, 3, 7 and 14
January 2025 |
Site
Inspection |
8, 15, 24 and
28 January 2025 |
The existing air quality
monitoring location AMS6 - Dragonair / CNAC (Group)
Building (HKIA) was handed over to Airport Authority Hong Kong on 31 March
2021. 1-hr and 24-hr TSP monitoring at AMS6 was temporarily suspended during
1 April 2021 to 7 August 2024. The site was closed on
29-31 January 2025, hence no water quality monitoring was arranged. |
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
0 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
0 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
0 |
0 |
Complaint
Log
There was no complaint
received in relation to the environmental impacts during this reporting month.
Notifications
of Summons and Prosecutions
There
were no notifications of summons or prosecutions received during this reporting
month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May 2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was
observed inside the perimeter silt curtain of Contract HY/2010/02 on 1 July
2013, as such the original impact water quality monitoring location at IS(Mf)9 was temporarily shifted outside the silt curtain. As advised by the Contractor of HY/2010/02 in August 2013, the perimeter
silt curtain was shifted to facilitate safe anchorage zone of construction
barges/vessels until end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N
since 1 July 2013. According to the
water quality monitoring team¡¦s observation on 24 March 2014, the original
monitoring location of IS(Mf)9 was no longer enclosed
by the perimeter silt curtain of Contract HY/2010/02. Thus, the impact water
quality monitoring works at the original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
The water quality
monitoring stations at IS10 (Coordinate: 812577E, 820670N) and SR5 (811489E,
820455N) are located inside Hong Kong International Airport (HKIA) Approach
Restricted Areas. The previously granted Vessel's Entry Permit for accessing
stations IS10 and SR5 were expired on 31 December 2016. During the permit
renewing process, the water quality monitoring location was shifted to IS10(N)
(Coordinate: 813060E, 820540N) and SR5(N) (Coordinate: 811430E, 820978N) on 2,
4 and 6 January 2017 temporarily. The permit has been granted by Marine
Department on 6 January 2017. Thus, the impact water quality monitoring works
at original monitoring location of IS10 and SR5 has been resumed since 9
January 2017.
Transect lines 2, 3, 4, 5,
6 and 7 for dolphin monitoring have been revised and transect line 24 has been
added due to the presence of a work zone to the north of the airport platform
with intense construction activities in association with the construction of
the third runway expansion for the Hong Kong International Airport. The EPD
issued a memo and confirmed that they had no objection on the revised transect
lines on 28 July 2017. The alternative dolphin transect lines are adopted
starting from August¡¦s dolphin monitoring.
The role and responsibilities as the ET Leader of the Contract was
temporarily taken up by Mr Willie Wong instead of Ms Claudine Lee from 25 September 2017 to 31 December 2017.
The topographical condition of the water monitoring
stations SR3 (Coordinate: 810525E, 816456N), SR4 (Coordinate: 814760E,
817867N), SR10A (Coordinate: 823741E, 823495N) and SR10B (Coordinate: 823686E,
823213N) cannot be accessed safely for undertaking water quality monitoring.
The water quality monitoring has been temporarily conducted at alternative
stations, namely SR3(N) (Coordinate 810689E, 816591N), SR4(N) (Coordinate:
814705E, 817859N) and SR10A(N) (Coordinate: 823644E, 823484N) since 1 September
2017. The water quality monitoring at station SR10B was temporarily conducted
at Coordinate: 823683E, 823187N on 1, 4, 6, 8 September 2017 and has been
temporarily fine-tuned to alternative station SR10B(N2) (Coordinate: 823689E,
823159N) since 11 September 2017. Proposal for permanently relocating the
aforementioned stations was approved by EPD on 8 January 2018.
The works
area WA5 was handed over to other party on 22 June 2013.
According to latest information received in July 2018, the works area
WA7 was handed over to other party on 28 February 2018 instead of 31 January
2018.
Original WQM stations IS8 and SR4(N) are located within the active work
area of TCNTE project and the access to the WQM stations IS8 (Coordinate:
E814251, N818412) and SR4(N) (Coordinate: E814705, N817859) are blocked by the
silt curtains of the Tung Chung New Town Extension (TCNTE) project. Alternative
monitoring stations IS8(N) (Coordinate: E814413, N818570) and SR4(N2)
(Coordinate: E814688, N817996) are proposed to replace the original monitoring
stations IS8 and SR4(N). Proposal for permanently relocating the aforementioned
stations was approved by EPD on 20 August 2019. The water quality monitoring has been conducted at stations IS8(N) and
SR4(N2) on 21 August 2019.
There were no marine
works conducted by Contract No. HY/2011/03 since July 2019. A proposal for
temporary suspension of marine related environmental monitoring (water quality
monitoring and dolphin monitoring for the Contract No. HY/2011/03) was justified
by the ET leader and verified by IEC in mid of September 2019 and it was
approved by EPD on 24 September 2019. Water quality monitoring and dolphin
monitoring for the Contract will not be conducted starting from 1 October 2019
until marine works (i.e. toe loading removal works) be resumed. As discussed
with Contract No. HY/2012/08, they will take up the responsibility from
Contract No. HY/2011/03 for the dolphin monitoring works starting from 1
October 2019.
According to information received in January 2020, the works area WA3
and WA4 were handed over to Highways Department on 23 December 2019 and 14
March 2019 respectively.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Manson Yeung instead of Mr Ray Yan since 18 May 2020.
Mr. Leslie Leung was Environmental Team Leader of the Contract for July
2020. The role and responsibilities as the Environmental Team Leader of the
Contract has been taken up by Ms. Claudine Lee with effective from 1 August
2020.
The existing air quality monitoring location AMS6 - Dragonair / CNAC (Group) Building (HKIA) was handed over to
Airport Authority Hong Kong on 31 March 2021. 1-hr and 24-hr TSP monitoring at
AMS6 was temporarily suspended starting from 1 April 2021. A new alternative
air quality monitoring location is still under processing.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Brian Tam instead of Mr Manson Yeung since 12 April 2021.
The role and
responsibilities as the IEC of the Contract has been taken up by Mr Adi Lee instead of Mr Brian Tam since 3 May 2022.
The role and responsibilities as the IEC of the Contract has been taken
up by Mr Brian Tam instead of Mr Adi Lee since 25 July 2022.
The role and responsibilities as the ENPO Leader of the Contract has
been taken up by Mr Louis Kwan from ANewR Consulting
Limited instead of Mr H.Y. Hui from Ramboll Hong Kong
Limited since 1 October 2022.
The role and responsibilities as the IEC of the Contract has been taken
up by Mr James Choi from ANewR Consulting Limited instead of Mr Brian Tam Ramboll Hong Kong
Limited since 1 October 2022.
The existing air quality monitoring location AMS6 - Dragonair / CNAC (Group) Building (HKIA) was handed over to
Airport Authority Hong Kong on 31 March 2021. 1-hr and 24-hr air quality
monitoring at AMS6 was temporarily suspended starting from 1 April 2021 and
resumed on 7 August 2024. 24-hr monitoring results at AMS6 are not available
due to unstable electricity supply on site and the solution for stable
electricity supply is under investigation, the monitoring has been resumed on
19 September 2024.
Future Key Issues
The future key issues include potential noise, air quality, water quality and
ecological impacts and waste management arising from the following construction
activities to be undertaken in the upcoming month:
¡P
Removal of Temporary
Toe Loading Platform at Portion X.
¡P
New reclamation along
the east coast of the approximately 23 hectares.
¡P
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main Bridge.
¡P
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
¡P
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
¡P
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
¡P
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the Dragonair Headquarters Building, including the construction
of buildings, connection roads and other associated facilities.
¡P
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Supervising Officer¡¦s Representative |
(Senior
Resident Engineer, SRE) |
Eddie Tsang |
3968 4802 |
2109 1882 |
Environmental Project Office / Independent
Environmental Checker |
Environmental Project Office Leader |
Louis Kwan |
9275 0975 |
3007 8448 |
Independent Environmental Checker |
James Choi |
6122
5213 |
3007 8448 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968 7002 |
2109 2588 |
Environmental Officer |
Federick Wong |
3968 7117 |
2109 2588 |
|
Environmental Team (Meinhardt Infrastructure and Environment
Limited) |
Environmental Team Leader |
Claudine Lee |
2859 5409 |
2559 0738 |
24 hours
complaint hotline |
--- |
--- |
5699 5730 |
--- |
|
Table 1.2 Construction Activities During Reporting Month
Description of
Activities |
Site Area |
Reinstatement
Works |
Portion X |
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ¡V Dragonair /
CNAC (Group) Building (HKIA) |
360 |
Table 2.2 Action
and Limit Levels for 24-hour TSP
Monitoring
Station |
Action Level,
µg/m3 |
Limit Level,
µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ¡V Dragonair /
CNAC (Group) Building (HKIA) |
173 |
260 |
Table 2.3 Air
Quality Monitoring Equipment
Equipment |
Brand and
Model |
Portable direct reading
dust meter (1-hour TSP) |
Sibata Digital Dust Indicator
(Model No. LD-5R) |
High Volume Sampler |
Tisch Environmental
Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Air
Sampler (Model No. TE-5170) |
Table 2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
AMS5 |
Ma Wan Chung Village
(Tung Chung) |
AMS6 |
Dragonair / CNAC (Group)
Building (HKIA) |
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
1-hour TSP |
Three times every 6 days while the highest dust
impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air
sensitive receivers. The following criteria were considered in the installation
of the HVS.
(i) A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
(ii) The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
(iii) A minimum of 2 meters separation from walls,
parapets and penthouse for rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and
access to the monitoring stations.
(vii) A secured supply of electricity was obtained to
operate the samplers.
(viii) The sampler was located more than 20 meters from any
dripline.
(ix) Any wire fence and gate, required to protect the
sampler, did not obstruct the monitoring process.
(x) Flow control accuracy was kept within ¡Ó2.5%
deviation over 24-hour sampling period.
(b) Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and
sufficient filters that were clean and without pinholes were selected.
(ii) All filters were equilibrated in the conditioning
environment for 24 hours before weighing. The conditioning environment
temperature was around
(iii) All filter papers were prepared and analysed by ALS
Technichem (HK) Pty Ltd., which is a HOKLAS
accredited laboratory and has comprehensive quality assurance and quality
control programmes.
(c) Field
Monitoring
(i) The power supply was checked to ensure the HVS
works properly.
(ii) The filter holder and the area surrounding the
filter were cleaned.
(iii) The filter holder was removed by loosening the four
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully.
(iv) The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter.
(v) The swing bolts were fastened to hold the filter
holder down to the frame. The
pressure applied was sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured
with the aluminium strip.
(vii) The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
(viii) A new flow rate record sheet was set into the flow
recorder.
(ix) On site temperature and atmospheric pressure
readings were taken and the flow rate of the HVS was checked and adjusted at
around 1.1 m3/min, and complied with the range specified in the
Updated EM&A Manual for HKLR (Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a
sampling period of 24 hours, and the starting time, weather condition and the
filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and
atmospheric pressure readings were taken and the final flow rate of the HVS was
checked and recorded.
(xiii) The final elapsed time was recorded.
(xiv) The sampled filter was removed carefully and folded
in half length so that only surfaces with collected
particulate matter were in contact.
(xv) It was then placed in a clean plastic envelope and
sealed.
(xvi) All monitoring information was recorded on a
standard data sheet.
(xvii) Filters were then sent to ALS Technichem
(HK) Pty Ltd. for analysis.
(d) Maintenance and Calibration
(i) The HVS and its accessories were maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using
TE
(iii) Calibration certificate of the HVSs are provided in
Appendix C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction
Manual as follows:-
(i)
Turn
the power on.
(ii) Close the air collecting opening cover.
(iii) Push the ¡§TIME SETTING¡¨ switch to [BG].
(iv) Push ¡§START/STOP¡¨ switch to perform background
measurement for 6 seconds.
(v) Turn the knob at SENSI ADJ position to insert the
light scattering plate.
(vi) Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨
is indicated in the display.
(vii) Push ¡§START/STOP¡¨ switch to perform automatic
sensitivity adjustment. This measurement takes 1 minute.
(viii) Pull out the knob and return it to MEASURE
position.
(ix) Push the ¡§TIME SETTING¡¨ switch the time set in the
display to 3 hours.
(x) Lower down the air collection opening cover.
(xi) Push ¡§START/STOP¡¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The
1-hour TSP meter was calibrated at 1-year intervals against a Tisch
Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High
Volume Air Sampler. Calibration certificates of the Laser Dust Monitors are
provided in Appendix C.
Table 2.6
Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring
Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
106 |
56-143 |
352 |
500 |
AMS6 |
91 |
40-137 |
360 |
500 |
Table 2.7 Summary
of 24-hour
TSP Monitoring Results During the Reporting Month
Monitoring
Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
54 |
29-73 |
164 |
260 |
AMS6 |
95 |
44-121 |
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ¡V Ma Wan
Chung Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900
hours on normal weekdays |
When one
documented complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
NL-52 |
Acoustic
Calibrator |
NC-74 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10
and L90 would be recorded. |
At least once
per week |
(a) The sound level
meter was set on a tripod at a height of
(b) The battery
condition was checked to ensure the correct functioning of the meter.
(c)
Parameters such
as frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency
weighting: A
(ii) time
weighting: Fast
(iii) time
measurement: Leq(30-minutes)
during non-restricted hours i.e. 07:00 ¡V 1900 on normal weekdays
(d) Prior to and
after each noise measurement, the meter was calibrated using the acoustic
calibrator for 94.0 dB(A) at 1000 Hz.
If the difference in the calibration level before and after measurement
was more than 1.0 dB(A), the measurement would be considered invalid and repeat
of noise measurement would be required after re-calibration or repair of the
equipment.
(e) During the
monitoring period, the Leq, L10
and L90 were recorded.
In addition, site conditions and noise sources were recorded on a
standard record sheet.
(f) Noise
measurement was paused during periods of high intrusive noise (e.g. dog
barking, helicopter noise) if possible. Observations were recorded when
intrusive noise was unavoidable.
(g) Noise monitoring
was cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The microphone
head of the sound level meter was cleaned with soft cloth at regular intervals.
(b) The
meter and calibrator were sent to the supplier or HOKLAS laboratory to check
and calibrate at yearly intervals.
(c) Calibration
certificates of the sound level meters and acoustic calibrators are provided in
Appendix C.
Table
3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring
Station |
Average Leq (30 mins), dB(A) |
Range of Leq (30 mins), dB(A) |
Limit Level Leq (30 mins), dB(A) |
NMS5 |
60 |
56-64 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved
Oxygen (mg/L) (surface, middle and bottom) |
Surface and
Middle |
5.0 |
4.2 except 5
for Fish Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity
(NTU) |
Depth average |
27.5 or 120%
of upstream control station¡¦s turbidity at the same tide of the same day; The action
level has been amended to ¡§27.5 and 120% of upstream control
station¡¦s turbidity at the same tide of the same day¡¨ since 25 March 2013. |
47.0 or 130%
of turbidity at the upstream control station at the same tide of same day; The limit
level has been amended to ¡§47.0 and 130% of turbidity at the
upstream control station at the same tide of same day¡¨ since 25 March 2013. |
Suspended
Solid (SS) (mg/L) |
Depth average |
23.5 or 120%
of upstream control station¡¦s SS at the same tide of the same day; The action
level has been amended to ¡§23.5 and 120% of upstream control
station¡¦s SS at the same tide of the same day¡¨ since 25 March 2013. |
34.4 or 130%
of SS at the upstream control station at the same tide of same day and 10mg/L
for Water Services Department Seawater Intakes; The limit
level has been amended to ¡§34.4 and 130% of SS at the upstream
control station at the same tide of same day and 10mg/L for Water Services
Department Seawater Intakes¡¨ since 25 March 2013 |
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3) For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4) The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
Table
4.2 Water Quality
Monitoring Equipment
Equipment |
Brand and
Model |
DO and
Temperature Meter, Salinity Meter, Turbidimeter and pH Meter |
YSI Model 6820
(V2) YSI Pro Quatro |
Positioning
Equipment |
Garmin GPS72H |
Water Depth
Detector |
Lowrance x-4 |
Water Sampler |
Kahlsio Water Sampler (Vertical) 2.2 L with messenger |
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring
Stations |
Parameter,
unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field
Stations: Sensitive Receiver
Stations: |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen
(DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P Suspended Solids (SS), mg/L |
Three times per week
during mid-ebb and mid-flood tides (within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored). |
Remark:
1) Original WQM stations IS8 and SR4(N) are located within the active work
area of Tung Chung New Town Extension (TCNTE) project and the access to the WQM
stations IS8 (Coordinate: E814251, N818412) and SR4(N) (Coordinate: E814705,
N817859) are blocked by the silt curtains of the TCNTE project. Alternative
monitoring stations IS8(N) (Coordinate: E814413, N818570) and SR4(N2)
(Coordinate: E814688, N817996) were proposed to replace the original monitoring
stations IS8 and SR4(N). Proposal for permanently relocating the aforementioned
stations was approved by EPD on 20 August 2019. The water quality monitoring
has been conducted at stations IS8(N) and SR4(N2) since 21 August 2019.
2) The access to the WQM station SR4(N2) (Coordinate:
E814688, N817996) is blocked by the silt curtains of the TCNTE project. Water
quality monitoring was temporarily conducted at alternative stations, namely
SR4(N3) (Coordinate: E814779, N818032). Proposal for permanently relocating the
SR4(N2) was approved by EPD on 3 March 2023. The water quality monitoring has
been conducted at stations SR4(N3) since 3 March 2023.
Table 4.4 Impact Water
Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |
|
Easting |
Northing |
||
IS5 |
Impact Station
(Close to HKLR construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station
(Close to HKLR construction site) |
812101 |
817873 |
IS7 |
Impact Station
(Close to HKBCF construction site) |
812244 |
818777 |
IS8(N) |
Impact Station
(Close to HKBCF construction site) |
814413 |
818570 |
IS(Mf)9 |
Impact Station
(Close to HKBCF construction site) |
813273 |
818850 |
IS10(N) |
Impact Station
(Close to HKBCF construction site) |
812942 |
820881 |
SR3(N) |
Sensitive
receivers (San Tau SSSI) |
810689 |
816591 |
SR4(N3)* |
Sensitive
receivers (Tai Ho Inlet) |
814779 |
818032 |
SR5(N) |
Sensitive
Receivers (Artificial Reef in NE Airport) |
812569 |
821475 |
SR10A(N) |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823644 |
823484 |
SR10B(N2) |
Sensitive
receivers (Ma Wan Fish Culture Zone) |
823689 |
823159 |
CS2(A) |
Control
Station (Mid-Ebb) |
805232 |
818606 |
CS(Mf)5 |
Control
Station (Mid-Flood) |
817990 |
821129 |
Remark: * The access to the WQM
station SR4(N2) (Coordinate: E814688, N817996) is blocked by the silt
curtains of the Tung Chung New Town Extension (TCNTE) project. Water quality
monitoring was temporarily conducted at alternative stations, namely SR4(N3)
(Coordinate: E814779, N818032) on 1 March 2023. Proposal for permanently
relocating the SR4(N2) was approved by EPD on 3 March 2023. The water quality
monitoring has been conducted at stations SR4(N3) since 3 March 2023. |
(a) The
in-situ water quality parameters including dissolved oxygen, temperature,
salinity and turbidity, pH were measured by multi-parameter meters.
(a) Digital Differential Global Positioning
Systems (DGPS) were used to ensure that the correct location was selected prior
to sample collection.
(b) Portable, battery-operated echo sounders
were used for the determination of water depth at each designated monitoring
station.
(c) All in-situ measurements were taken at 3
water depths, 1 m below water surface, mid-depth and 1 m above sea bed, except
where the water depth was less than 6 m, in which case the mid-depth station
was omitted. Should the water depth be less than 3 m, only the mid-depth
station was monitored.
(d) At each measurement/sampling depth, two
consecutive in-situ monitoring (DO concentration and saturation, temperature,
turbidity, pH, salinity) and water sample for SS. The probes were retrieved out
of the water after the first measurement and then re-deployed for the second
measurement. Where the difference in the value between the first and second
readings of DO or turbidity parameters was more than 25% of the value of the
first reading, the reading was discarded and further readings were taken.
(e) Duplicate samples from each independent
sampling event were collected for SS measurement. Water samples were collected
using the water samplers and the samples were stored in high-density polythene
bottles. Water samples collected were well-mixed in the water sampler prior to
pre-rinsing and transferring to sample bottles. Sample bottles were pre-rinsed
with the same water samples. The sample bottles were then be packed in
cool-boxes (cooled at 4oC without being frozen), and delivered to
ALS Technichem (HK) Pty Ltd. for the analysis of
suspended solids concentrations. The laboratory determination work would be
started within 24 hours after collection of the water samples. ALS Technichem (HK) Pty Ltd. is a HOKLAS accredited laboratory
and has comprehensive quality assurance and quality control programmes.
(f) The analysis method and detection limit for
SS is shown in Table 4.5.
Table 4.5 Laboratory
Analysis for Suspended Solids
Parameters |
Instrumentation |
Analytical
Method |
Detection
Limit |
Suspended Solid (SS) |
Weighting |
APHA 2540-D |
0.5mg/L |
(g) Other relevant data were recorded, including
monitoring location / position, time, water depth, tidal stages, weather
conditions and any special phenomena or work underway at the construction site
in the field log sheet for information.
Table 5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster |
|
NEL |
NWL |
|
Action Level |
STG < 4.2 & ANI < 15.5 |
STG < 6.9
& ANI < 31.3 |
Limit Level |
(STG < 2.4
& ANI < 8.9) and (STG < 3.9 & ANI < 17.9) |
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be trigger if either NEL or NWL fall below the criteria; LL will
be triggered if both NEL and NWL
fall below the criteria.
Table 5.2 Co-ordinates
of Transect Lines
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
815456 |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805476 |
820800* |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805476 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
821150* |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
821500* |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
821850* |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
822150* |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
822000* |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
821123 |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
821303 |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813425 |
821176 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813425 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818853 |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
24* |
Start
Point |
805476* |
815900* |
12 |
End Point |
815542 |
824882 |
|
24* |
End
Point |
805476* |
819100* |
Note:
Co-ordinates in red and marked with asterisk are revised co-ordinates of
transect line.
Table 5.3 Dolphin encounter rates deduced from
the two sets of surveys (two surveys in each set) in January 2025 in
Northeast (NEL) and Northwest Lautau (NWL)
|
Encounter rate (STG) (no. of on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings
per 100 km of survey effort) |
|
Primary Lines Only |
Primary Lines Only |
||
NEL |
Set 1: January
2nd / 3rd |
0.0 |
0.0 |
Set 2: January
7th / 14th |
0.0 |
0.0 |
|
NWL |
Set 1: January
2nd / 3rd |
1.7 |
1.7 |
Set 2: January
7th / 14th |
3.4 |
3.4 |
Table
5.4 Overall dolphin encounter rates (sighting per 100 km of survey effort) from
all surveys conducted in January 2025 on primary lines only as well as both
primary lines and secondary lines in Northeast and Northwest Lantau
|
Encounter rate (STG)
(no. of on-effort
dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
||
Primary Lines Only |
Both Primary and Secondary Lines |
Primary Lines Only |
Both Primary and Secondary Lines |
|
Northeast Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest Lantau |
2.6 |
1.8 |
2.6 |
1.8 |
- Buckland, S. T., Anderson,
D. R., Burnham, K. P., Laake, J. L., Borchers, D. L., and Thomas, L. 2001. Introduction to distance sampling:
estimating abundance of biological populations. Oxford University Press, London.
- Hung, S. K. 2021. Monitoring of Marine Mammals in Hong
Kong waters: final report (2020-21).
An unpublished report submitted to the Agriculture, Fisheries and
Conservation Department, 154 pp.
- Jefferson, T. A. 2000. Population biology of the Indo-Pacific
hump-backed dolphin in Hong Kong waters.
Wildlife Monographs 144:1-65.
Table 6.1 Summary
of Environmental Site Inspections
Date of Audit |
Observations |
Actions Taken
by Contractor / Recommendation |
Date of
Observations Closed |
No particular environmental issue was recorded during the
site inspection. |
N.A. |
N.A. |
|
15 January 2025 |
No particular environmental issue
was recorded during the site inspection. |
N.A. |
N.A. |
24 January 2025 |
No particular environmental issue
was recorded during the site inspection. |
N.A. |
N.A. |
28 January 2025 |
No particular environmental issue
was recorded during the site inspection. |
N.A. |
N.A. |
Table 7.1 Construction
Activities for February 2025
Site Area |
Description of Activities |
Portion X |
Reinstatement Works |