Quarterly EM&A
Report No. 2
(Covering the Period
from 1 June 2016 to 31 August 2016)
20 Sep 2016
Revision 0
Main
Contractor
Environmental Team

Contents
Executive Summary
1...... Introduction.. 1
1.1
Basic Project Information. 1
1.2
Project Organisation. 1
1.3
Construction Programme. 1
1.4
Construction Works Undertaken During the Reporting Period. 2
2....... EM&A
Requirement 3
2.1
Summary of EM&A Requirements. 3
2.2
Monitoring Requirements. 4
2.3
Action and Limit Levels. 4
2.4
Event Action Plans. 4
2.5
Mitigation Measures. 5
3....... Environmental
Monitoring and Audit 6
3.1
Air Quality Monitoring Results. 6
3.2
Noise Monitoring Results. 6
3.3
Implementation of Environmental Measures. 6
3.4
Advice on the Solid and Liquid Waste Management Status. 6
3.5
Environmental Licenses and Permits. 6
4....... Summary
of Exceedance, Complaint, Notification of Summons and Successful Prosecution.. 7
4.1
Summary of Exceedance of the Environmental Quality Performance Limit 7
4.2
Summary of Complaints, Notification of Summons and Successful
Prosecution. 7
5....... Comments,
Recommendations and Conclusion.. 8
5.1
Comments. 8
5.2
Recommendations. 8
5.3
Conclusions. 9
Figures
Figure 2.1
Location of Air Quality Monitoring Stations
Figure 2.2
Location of Noise Monitoring Stations
Appendices
Appendix
A Location of Works Areas
Appendix
B Project Organization for Environmental Works
Appendix
C Construction Programme
Appendix
D Event and Action Plan
Appendix
E Implementation Schedule for Environmental
Mitigation Measures (EMIS)
Appendix
F Site Audit Findings and Corrective
Actions
Appendix
G Waste flow Table
Appendix
H Environmental Licenses and Permits
Appendix I
Statistics on Environmental Complaints,
Notification of Summons and Successful Prosecutions
Executive Summary
This Quarterly Environmental
Monitoring and Audit (EM&A) Report is prepared for Contract HY/2014/05 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) ¡V
Remaining Ancillary Buildings and Facilities (hereafter referred to as ¡§the
Contract¡¨) for the Highways Department of Hong Kong Special Administrative
Region (HKSAR). The Contract was awarded to Leighton ¡V Chun Wo Joint Venture
(hereafter referred to as ¡§the Contractor¡¨) and Atkins China Limited was
appointed as the Environmental Team (ET) by the Contractor.
The Contract is part of Hong
Kong ¡V Zhuhai ¡V Macao Bridge HKBCF which is a ¡§Designated Project¡¨, under
Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) (Cap 499)
and Environmental Impact Assessment (EIA) Report (Register No. AEIAR-145/2009)
was prepared for the Project. The current Environmental Permit (EP) No.
EP-353/2009/K for HKBCF was issued on 11 April 2016. These documents are
available through the EIA Ordinance Register. The construction works of the
Contract commenced on 29 February 2016.
Atkins China Limited has been
appointed by the Contractor to implement the Environmental Monitoring &
Audit (EM&A) programme for the Contract in accordance with the Updated
EM&A Manual for HKBCF (Version1.0) and will be providing environmental team
services to the Contract.
This is the second Quarterly
EM&A Report for the Contract which summarizes findings of the EM&A
works during the reporting period from 1 June 2016 to 31 August 2016.
Environmental Monitoring and
Audit Progress
The EM&A programme was
undertaken in accordance with the Updated EM&A Manual for HKBCF (Version
1.0). It should be noted that the air quality and noise monitoring works for
the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao
Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between Scenic Hill and
HKBCF. The ET of the Contract or another ET of the HZMB project is
required to conduct impact air quality monitoring at AMS6 and AMS7 and noise
monitoring at NMS2 and NMS3B as part of EM&A programme if these monitoring
stations are no longer covered under Contract Nos. HY/2010/02 and HY/2011/03.
However, this is subject to ENPO¡¦s final decision on which ET should
carry out the monitoring work at these stations.
The dates of environmental site
inspection during the reporting period are listed below:
Environmental
Site Inspection Date
|
June 2016
|
July 2016
|
August
2016
|
1, 8, 15, 22 and 29
|
6, 13, 22 and 27
|
3, 10, 17, 24 and 31
|
Breaches of Action and Limit
Levels
Summary of Action and Limit
Level exceedance of 1-hr TSP level and 24-hr TSP level at station AMS6 shall be
referred to the monthly EM&A Reports (for June, July and August 2016)
prepared by Contract No. HY/2011/03.
There was no Action and Limit
Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7 by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
There was no Action and Limit
Level exceedance for noise recorded at NMS2 and NMS3B by the Environmental Team
of Contract No. HY/2010/02 during the reporting period.
Implementation of
Environmental Measures
Site inspections were carried
out on a weekly basis to monitor the implementation of proper environmental
pollution control and mitigation measures for the Project. Potential
environmental impacts due to the construction activities were monitored and reviewed.
Complaint Log
There was no complaint received
in relation to the environmental impact during the reporting period.
Notifications of Summons and
Successful Prosecutions
There was no notification of
summon or prosecution received during this reporting period.
Reporting Change
There is no reporting change
during the reporting period.
1
Introduction
1.1
Basic Project Information
1.1.1 This Quarterly
Environmental Monitoring and Audit (EM&A) Report is prepared for Contract HY/2014/05
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ¡V
Remaining Ancillary Buildings and Facilities (hereafter referred to as ¡§the
Contract¡¨) for the Highways Department of Hong Kong Special Administrative
Region. The Contract was awarded to Leighton ¡V Chun Wo Joint Venture (hereafter
referred to as ¡§the Contractor¡¨) and Atkins China Limited was appointed as the
Environmental Team (ET) by the Contractor.
1.1.2 The Contract is part of Hong Kong ¡V
Zhuhai ¡V Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) which is a
¡§Designated Project¡¨, under Schedule 2 of the Environmental Impact Assessment
Ordinance (EIAO) (Cap 499). An Environmental Impact Assessment (EIA) Report
(Register No. AEIAR-145/2009) was prepared for the Project. The current
Environmental Permit (EP) No. EP-353/2009/K for HKBCF was issued on 11 April
2016. These documents are available through the EIA Ordinance Register. The
construction works of the Contract commenced on 29 February 2016. The works
areas of the Contract are shown in Appendix A.
1.1.3
This is the second Quarterly EM&A Report for the
Contract which summarizes the audit findings of the EM&A programme during
the reporting period from 1 June 2016 to 31 August 2016.
1.2.1 The project organization structure
and lines of communication with respect to the on-site environmental management
structure is shown in Appendix
B. The key personnel contact names and numbers are summarized in Table
1.1.
Table 1.1
Contact Information of Key Personnel
Party
|
Position
|
Name
|
Telephone
|
Fax
|
Engineer
or Engineer¡¦s Representative
(AECOM Asia Co. Ltd.)
|
Chief
Resident Engineer
|
Darrel
Kingan
|
3958
7339
|
3468
2076
|
Environmental
Project Office / Independent Environmental Checker
(Ramboll Environ Hong Kong Limited)
|
Environmental
Project Office Leader
|
Y.
H. Hui
|
3465
2888
|
3465
2899
|
Independent
Environmental Checker
|
Raymond
Dai
|
3465
2888
|
3465
2899
|
Contractor
(Leighton ¡V Chun Wo Joint Venture)
|
Site
Agent
|
Albert
Chan
|
3973
0514
|
3621
0180
|
Environmental
Officer
|
Donald
Ip
|
6461
8635
|
3621
0180
|
Environmental
Team
(Atkins China Limited)
|
Environmental
Team Leader
|
Sharifah
Or
|
2972
1802
|
2890
6343
|
24
hours complaint hotline
|
---
|
---
|
3958
7300
|
---
|
1.3
Construction Programme
1.3.1 A copy of the Contractor¡¦s
construction programme is provided in Appendix C.
1.4
Construction Works Undertaken During the Reporting Period
1.4.1 A summary of the construction
activities undertaken during this reporting period is shown below:
¡P
Earth Works for Customs and Excise Department
Outbound Cargo Examination Building and Examination Platform (Building 023),
Inbound Private Car Annexure (Building 025), Outbound X-Ray Scan Building
(Building 053) and Inbound X-Ray Scan Tunnel (Building 058);
¡P
Binding of Buildings 025, 053 and 058;
¡P
Construction of Reinforced Concrete Structure
of Buildings 023, 025, 053, 058 and Inbound X-Ray Scan Building (Building 059);
and
¡P
Temporary Drainage System of WA3 Storage Area.
1.4.2
2.1
Summary of EM&A Requirements
2.1.1 The
EM&A programme was undertaken in accordance with the Updated EM&A
Manual for HKBCF (Version 1). It should be noted that the air quality and noise monitoring works for
the Contract are covered by Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao
Bridge HKBCF ¡V Reclamation Works and Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao
Bridge Hong Kong Link Road ¡V Section between Scenic Hill and HKBCF. The ET of
the Contract or another ET of the HZMB project is required to conduct impact
air quality monitoring at AMS6 and AMS7 and noise monitoring at NMS2 and NMS3B
as part of EM&A programme if these monitoring stations are no longer
covered under Contract Nos. HY/2010/02 and HY/2011/03. However, this is subject
to ENPO¡¦s final decision on which ET should carry out the monitoring work at
these stations.
2.1.2 A summary of air and noise
monitoring locations are presented in Table 2.1. The location of air
quality and noise monitoring stations are shown as in Figure 2.1 and Figure 2.2,
respectively.
Table 2.1
Summary of Impact EM&A Requirements
Environmental Monitoring
|
ID
|
Location Description
|
Air Quality
|
AMS6(1)
|
Dragonair/CNAC
(Group) Building
|
AMS7(1)
|
Hong Kong
SkyCity Marriott Hotel
|
Noise
|
NMS2(2)
|
Seaview Crescent
|
NMS3B(2),(3)
|
Site Boundary of Site Office
Area at Works Area WA2
|
Remarks:
(1) The ET of this Contract should conduct impact air quality monitoring at
the AMS listed in the table as part of EM&A programme according to the
latest notification from ENPO when the monitoring station(s) is/are no longer covered
by another ET of the HZMB project.
(2) The ET of this Contract should conduct impact noise monitoring at the
NMS listed in the table as part of EM&A programme according to the latest
notification from ENPO when the monitoring station(s) is/are no longer covered
by another ET of the HZMB project.
(3) The Action and Limit Levels for schools will be applied for this
alternative monitoring location.
2.2
Monitoring Requirements
2.2.1 The monitoring requirements,
monitoring equipment, monitoring parameters, frequency and duration, monitoring
methodology, monitoring schedule, meteorological information are detailed in
the monthly EM&A Reports prepared for Contract Nos. HY/2010/02 and
HY/2011/03.
2.3
Action and Limit Levels
2.3.1 The Action and Limit Level for 1-hr
TSP and 24-hr TSP are provided in Table 2.2 and Table 2.3,
respectively.
Table 2.2
Action and Limit Levels for 1-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS6 ¡V Dragonair/CNAC (Group) Building (HKIA)
|
360
|
500
|
AMS7 ¡V Hong Kong SkyCity Marriott Hotel
|
370
|
Table 2.3 Action and
Limit Levels for 24-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS6 ¡V Dragonair/CNAC (Group) Building (HKIA)
|
173
|
260
|
AMS7 ¡V Hong Kong SkyCity Marriott Hotel
|
183
|
2.3.2 If exceedance(s) at these station(s)
is/are recorded by the ET of the Contract or referred by the other ET under the
HZMB project to the Contract, the ET of the Contract will carry out an
investigation and findings
will be reported in the monthly EM&A Report.
2.3.3
The Action and Limit Levels for construction noise are defined in Table
2.4.
Table 2.4
Action and Limit Level for Construction Noise
Parameter
|
Action Level
|
Limit Level
|
07:00 ¡V 19:00
hours on normal
weekdays
|
When one documented complaint is received
|
75 dB(A)*
|
Notes:
If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.
* Reduce to 70
dB(A) for schools and 65 dB(A) during school examination period.
2.3.4 If exceedance(s) at these station(s)
is/are recorded by the ET of the Contract or referred by the other ET under the
HZMB project to the Contract, the ET of the Contract will carry out an
investigation and findings
will be reported in the monthly EM&A Report.
2.4.1 The Event Actions Plans for air
quality and noise are provided in Appendix D.
2.5.1 Environmental
mitigation measures for the contract were recommended in the approved EIA
Report. Appendix E
lists the recommended mitigation measures and the implementation
status.
3 Environmental Monitoring and Audit
3.1
Air Quality Monitoring Results
3.1.1 The monitoring results for AMS6 and
AMS7 are reported in the monthly EM&A Reports (for June, July and
August 2016) prepared for
Contract Nos. HY/2011/03 and HY/2010/02, respectively.
3.1.2 Summary of Action and Limit Level
exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be referred to
the monthly EM&A Reports (for June, July and August 2016) prepared by Contract No. HY/2011/03.
3.1.3 There was
no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7 recorded by the ET
of Contract No. HY/2010/02 during the reporting period.
3.2
Noise Monitoring Results
3.2.1 The monitoring results for NMS2 and
NMS3B are reported in the monthly EM&A Reports (for June, July and
August 2016) prepared for
Contract No. HY/2010/02.
3.2.2 No noise
exceedances were recorded at stations NMS2 and NMS3B by the ET of Contract No.
HY/2010/02 during the reporting period.
3.3
Implementation of Environmental Measures
3.3.1
In response to the site audit findings, the Contractor carried out
corrective actions. Details of site audit findings and the corrective actions
during the reporting period are presented in Appendix F.
3.3.2
A summary of the Implementation Schedule of Environmental Mitigation
Measures (EMIS) is presented in Appendix E. Most of the necessary
mitigation measures were implemented properly.
3.3.3 The
Contractor waters 8 times per day on all exposed soil within the Contract site
and associated works areas when construction activities are being undertaken.
3.4
Advice on the Solid and Liquid Waste Management Status
3.4.1 The
Contractor registered as a chemical waste producer for the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
3.4.2 The summary
of waste flow table is detailed in Appendix G.
3.4.3 The
Contractor was reminded that chemical waste containers should be properly
treated and stored temporarily in designated chemical waste storage area on
site in accordance with the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes.
3.5
Environmental Licenses and Permits
3.5.1 The valid
environmental licenses and permits during the reporting period are summarized
in Appendix H.
4 Summary of Exceedance, Complaint, Notification
of Summons and Successful Prosecution
4.1
Summary of Exceedance of the Environmental Quality Performance Limit
4.1.1
Summary of Action and
Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be
referred to the monthly EM&A Reports (for June, July and August
2016) prepared by Contract No.
HY/2011/03.
4.1.2 There was
no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7 by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
4.1.3 There was no Action and Limit Level
exceedance for noise recorded at NMS2 and NMS3B by the Environmental Team of
Contract No. HY/2010/02 during the reporting period.
4.2
Summary of Complaints, Notification of Summons and Successful
Prosecution
4.2.1
There was no complaint
received in relation to the environmental impact during the reporting period.
No notification of summons and prosecution was received during the reporting
period.
4.2.2 Statistics
on notifications of summons and successful prosecutions are summarized in Appendix I.
5 Comments, Recommendations and
Conclusion
5.1.1 According to the environmental site
inspections undertaken during the reporting period, the following
recommendations were provided:
¡P
The Contractor was reminded to provide water
spraying on the haul road.
¡P
The Contractor was reminded to clear the
stagnant water/ chemicals inside the drip tray.
¡P
The Contractor was reminded to provide a drip
tray for chemicals containers.
¡P
The Contractor was reminded to clear the
rubbish/food container on site.
¡P
The Contractor was reminded to remove general refuses/construction
waste regularly.
¡P
The Contractor was reminded to close all the
doors/panels of machinery during its operation.
¡P
The Contractor was reminded to store chemicals
with proper containers.
¡P
The Contractor was reminded to clear any oil
stain on the ground.
¡P
The Contractor was reminded to provide proper
mitigation measures for jet grouting works to prevent fugitive dust emission.
5.1.2 A summary
of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is
presented in Appendix E.
Most of the necessary mitigation measures were implemented properly.
5.2.1 With implementation of the
recommended environmental mitigation measures, the contract¡¦s environmental
impacts were considered environmentally acceptable. The weekly environmental
site inspections ensured that all the environmental mitigation measures
recommended were effectively implemented.
5.2.2 The recommended environmental
mitigation measures, as included in the EM&A programme, effectively
minimize the potential environmental impacts from the contract. Also, the
EM&A programme effectively monitored the environmental impacts from the
construction activities and ensure the proper implementation of mitigation
measures. No particular recommendation was advised for the improvement of the
programme.
5.3.1
The construction works
of the Contract commenced on 29 February 2016. This is the second Quarterly
EM&A Report summarizes findings of the EM&A works during the reporting
period from 1 June 2016 to 31 August 2016.
5.3.2
Summary of Action and
Limit Level exceedance of 1-hr TSP level and 24-hr TSP level at AMS6 shall be
referred to the monthly EM&A Reports (for June, July and August
2016) prepared by Contract No.
HY/2011/03.
5.3.3 There was
no Action and Limit Level exceedance of 1-hr TSP level and 24-hr TSP level recorded at AMS7 by the
Environmental Team of Contract No. HY/2010/02 during the reporting period.
5.3.4
There was no Action and Limit Level exceedance for noise recorded at
NMS2 and NMS3B by the Environmental Team of Contract No. HY/2010/02 during the
reporting period.
5.3.5 Environmental site inspections were
carried out on 1, 8, 15, 22 and 29 June 2016, 6, 13, 22 and 27 July 2016 and 3,
10, 17, 24 and 31 August 2016. Recommendations on remedial actions were given
to the Contractors for the deficiencies identified during the site inspections.
5.3.6 There was
no complaint received in relation to the environmental impact during the
reporting period.
5.3.7 No notification of summons and
successful prosecution was received during the reporting period.