TABLE OF CONTENTS
Page
1.4 Summary
of Construction Works
2 Summary of EM&A Programme
Requirements
2.2 Environmental
Quality Performance (Action/Limit Levels)
2.3 Environmental
Mitigation Measures
3.5 Environmental
Site Inspection and Audit
4 Advice on the Solid and Liquid Waste Management Status
4.1 Summary
of Solid and Liquid Waste Management
5 Implementation Status of Environmental Mitigation Measures
5.1 Implementation
Status of Environmental Mitigation Measures
6 Summary of Exceedances of the
Environmental Quality Performance Limit
6.1 Summary
of Exceedances of the Environmental Quality Performance Limit
7 Summary of Complaints,
Notification of Summons and Successful Prosecutions
7.1 Summary
of Environmental Complaints, Notification of Summons and Successful
Prosecutions
8 Comments, recommendations and
Conclusions
8.1 Comments
on mitigation measures
8.2 Recommendations
on EM&A Programme
List of Tables
Table 1.1 Contact Information of Key Personnel
Table 3.1 Summary of Number of Monitoring Events for 1-hr &
24-hr TSP Concentration
Table 3.2 Summary of Number of Exceedances for 1-hr & 24-hr
TSP Monitoring
Table 3.3 Summary of Number of Monitoring Events for Impact
Noise
Table 3.4 Summary of Number of Monitoring Exceedances for Impact Noise
Table 3.5 Summary of Water Quality Exceedances in June 2016 ¡V August 2016
Table 3.6 Summary of Key Dolphin Survey Findings in June 2016 ¡V August 2016
Table 3.7 Summary of STG and ANI encounter rates in June 2016 ¡V August 2016
Figures
Figure 1 General
Contract Layout Plan
Figure 2 Impact
Air Quality and Noise Monitoring Stations and Wind Station
Figure 3 Impact Water Quality Monitoring Stations
Figure 4 Impact Dolphin
Monitoring Line Transect Layout Map
Figure 5 Environmental
Complaint Handling Procedure
List of Appendices
Appendix A Contract
Organization for Environmental Works
Appendix B Three Month Rolling Construction
Programmes
Appendix C Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Summary of Action
and Limit Levels
Appendix E Graphical
Presentation of Impact
Air Quality Monitoring Results
Appendix F Graphical
Presentation of Impact
Daytime Construction Noise Monitoring Results
Appendix G Graphical
Presentation of Impact
Water Quality Monitoring Results
Appendix
H Impact Dolphin Monitoring
Survey Findings and Analysis
Appendix I Quarterly Summary of Waste Flow Table
This report documents the findings of EM&A works conducted in the period between 1 June 2016 and 31 August 2016. As informed by the Contractor, major activities in the reporting quarter were:-
Marine-base
- Sloping
Seawalls
- Rubble
Mound Seawall
- Maintenance
of silt curtain
Land-base
- Surcharge
removal & laying
- Deep
Cement Mixing
- Installations
of Precast Culverts except sloping outfalls
- Construction
of Permanent Seawall
- Maintenance
works of Site Office at Works Area WA2
- Maintenance
works of Public Works Regional Laboratory at Works Area WA3
- Maintenance
of Temporary Marine Access at Works Area WA2
A summary of monitoring and audit activities conducted in
the reporting quarter is listed below:
24-hour Total Suspended Particulates (TSP) monitoring 1-hour TSP monitoring |
16 sessions 16 sessions |
Noise monitoring |
12 sessions |
Impact water quality monitoring |
39 sessions |
Impact dolphin monitoring |
6 surveys |
Joint Environmental site inspection |
13 sessions |
All 1-Hour TSP and 24-Hour TSP
results were below the Action and Limit Level in the reporting quarter.
Breaches of
Action and Limit Levels for Water Quality
Breaches
of Action and Limit Levels for Impact Dolphin Monitoring
One (1) Limit Level exceedance of
dolphin monitoring was recorded in the reporting quarter. After investigation,
it was concluded that the HZMB works is one of the contributing factors
affecting the dolphins. It was also concluded the contribution of impacts due
to the HZMB works as a whole (or individual marine contracts) cannot be
quantified nor separate from the other stress factors. Event Action Plan for
Impact Dolphin Monitoring was triggered. For detail of investigation, please
refer to appendix L.
Implementation
Status and Review of Environmental Mitigation Measures
Most of the recommended mitigation
measures, as included in the EM&A programme, were implemented properly in
the reporting quarter.
The recommended environmental mitigation measures effectively minimize the potential environmental impacts from the Project. The EM&A programme effectively monitored the environmental impacts from the construction activities and ensure the proper implementation of mitigation measures. No particular recommendation was advised for the improvement of the programme.
Moreover, regular review and checking on the construction methodologies, working processes and plants were carried out to ensure the environmental impacts were kept minimal and recommended environmental mitigation measures were implemented effectively.
Complaint,
Notification of Summons and Successful Prosecution
1 complaint about marine litter near Tuen Mun Ferry Pier
was received on 16 Jul 2016, 9:19am. The complainant complained that pollution
was observed at Tuen Mun Ferry Pier and queried whether the pollutant came from
the construction sites of the Lantau area or bridge construction. After
investigation, it is considered the marine litter floating near the Tuen Mun
Ferry Pier is unlikely to be related to this Contract.
No notification of summons or
prosecution was received in the reporting period
Table 1.1 Contact Information of Key Personnel
Position |
Name |
Telephone |
Fax |
|
Engineer¡¦s Representative (ER) (Ove Arup & Partners Hong
Kong Limited) |
Chief Resident Engineer |
Paul
Appleton |
3698 5889 |
2698 5999 |
IEC / ENPO (Ramboll Environ Hong Kong Limited) |
Independent Environmental Checker |
Raymond Dai |
3465 2888 |
3465 2899 |
Environmental Project Office Leader |
Y. H. Hui |
3465 2850 |
3465 2899 |
|
Contractor (China Harbour Engineering Company Limited) |
Environmental Officer |
Louie Chan
|
36932254 |
2578 0413 |
24-hour Hotline |
Alan C.C. Yeung |
9448 0325 |
-- |
|
ET (AECOM Asia Company Limited) |
ET Leader |
Echo Leong |
3922 9280 |
2317 7609 |
Marine-base
- Sloping Seawalls
- Rubble Mound Seawall
- Maintenance of silt curtain
Land-base
- Surcharge removal & laying
- Deep Cement Mixing
- Installations of Precast
Culverts except sloping outfalls
- Construction of Permanent
Seawall
- Maintenance works of Site
Office at Works Area WA2
- Maintenance works
of Public Works Regional Laboratory at Works Area WA3
- Maintenance of Temporary
Marine Access at Works Area WA2
Table 3.1 Summary of Number of Monitoring Events for 1-hr & 24-hr TSP
Concentration
Monitoring Parameter |
Location |
No. of monitoring events |
||
June 16 |
July 16 |
August 16 |
||
1-hr TSP |
AMS2 |
18 |
15 |
15 |
AMS3B |
18 |
15 |
15 |
|
AMS7 |
18 |
15 |
15 |
|
24-hr TSP |
AMS2 |
6 |
5 |
5 |
AMS3B |
6 |
5 |
5 |
|
AMS7 |
6 |
5 |
5 |
Table 3.2 Summary of Number of Exceedances for 1-hr & 24-hr TSP Monitoring
Monitoring Parameter |
Location |
Level of Exceedance |
Numbers of Exceedance |
||
June 16 |
July 16 |
August 16 |
|||
1-hr TSP |
AMS2 |
Action |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
||
AMS3B |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
AMS7 |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
|
Total |
0 |
0 |
0 |
|
24-hr TSP |
AMS2 |
Action |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
||
AMS3B |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
AMS7 |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
|
Total |
0 |
0 |
0 |
Table 3.3 Summary of Number of Monitoring Events for Impact Noise
Monitoring Parameter |
Location |
No. of monitoring events |
||
June 16 |
July 16 |
August 16 |
||
NMS2 |
4 |
4 |
4 |
|
NMS3B |
4 |
4 |
4 |
Table 3.4 Summary of Number of Monitoring Exceedances for Impact Noise
Monitoring Parameter |
Location |
Level of Exceedance |
Level of Exceedance |
||
June 16 |
July 16 |
August 16 |
|||
NMS2 |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
NMS3B |
Action |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
||
|
Total |
0 |
0 |
0 |
Table 3.5 Summary of Water Quality Exceedances in June 2016 ¡V August 2016
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Total |
||||||
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
||
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)6 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS7 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS8 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)9 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS10 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)11 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS(Mf)16 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
IS17 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR3 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR4(N) |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR5 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR6 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR7 |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR10A |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
SR10B (N) |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Note: S: Surface;
M: Mid-depth;
Table 3.6 Summary
of Key Dolphin Survey Findings in June 2016 ¡V August 2016
Number of Impact Surveys Completed^ |
6 |
Survey Distance Travelled under Favourable On- Effort Condition |
639.7km |
Number of Sightings |
13 sightings (9 sightings are ¡¨on effort¡¨ (which are all under
favourable condition), 4 sightings are ¡§opportunistic¡¨) |
Number of dolphin individual sighted |
3.7 individuals (the best estimated group size) |
Dolphin Encounter Rate# |
NEL: 0 NWL: 2.1 |
Dolphin Group Size |
Average of NEL: 0 Average of NWL: 3.7 Varied from 1-9 individuals |
Most Often frequent dolphin sighting area |
Northern Sha Chau and Lung Kwu Chau Marine Park, the western limit of
NWL and Tai O area. |
Table 3.7 Summary
of STG and ANI encounter rates in
June
2016 ¡V August 2016 |
||||
NEL |
NWL |
Level Exceeded |
|
|
STG* |
0 |
1.4 |
Limit |
|
ANI** |
0 |
4.6 |
|
*Quarterly Average Encounter Rate of Number of Dolphin
Sightings (STG) presents averaged encounter rates of the three monitored months
in terms of groups per 100km per survey event.
STG Encounter rate = (Average of (total number
sighting/total effort) of 1st and 2nd completed survey# of 1st month+ Average
of (total number sighting/total effort) of 1st and 2nd completed survey# of 2nd
month + Average of (total number sighting/total effort) of 1st and 2nd
completed survey# of 3rd month)/3*100km
**Quarterly Average Encounter Rate of Total Number
of Dolphins (ANI) presents averaged encounter rates of the three monitored
months in terms of individuals per 100km per survey event.
ANI Encounter rate = (Average of (total number of
Individual/total effort) of 1st and 2nd completed survey# of 1st month+ Average
of (total number of Individual/total effort) of 1st and 2nd completed survey#
of 2nd month + Average of (total number of Individual/total effort) of 1st and
2nd completed survey# of 3rd month +)/3*100km
Noise
Water Quality
Chemical and Waste Management
Landscape and Visual Impact
Others
1: Review of the information and
provided by the complainant
2: Review the work activities
conducted by Contract HY/2010/02 HKBCF Reclamation on 16 July 2016.
3. Review site condition
- The
photo provided by the complainant was reviewed and it shows that marine litter
floating on sea near Tuen Mun Ferry Pier.
- Information provided by the
Contractor was checked, marine activities being conducted by Contract
HY/2010/02 on 16 July 2016 were accroprode/rock-fill placement for the
construction of the seawall by using a pelican with mechanical grab. In
addition, since the location of Tuen Mun Ferry Pier is approximately 5km away
from the active works contract HY/2010/02, these construction activities are
unlikely related to the floating litter on sea observed near Tuen Mun Ferry
Pier on 16 July 2016.
- Joint
site inspection was also conducted on 21 July 2016 with the Contractor, IEC, ET
and RSS. No litter was observed on sea during the inspection of the perimeter
of HKBCF reclamation works.
- As
such, it is considered the marine litter floating near the Tuen Mun Ferry Pier
is unlikely to be related to this Contract.
Air Quality Impact
¡P
All working plants and vessels on site should be regularly
inspected and properly maintained to avoid dark smoke emission.
¡P
All vehicles should be washed to remove any dusty materials before
leaving the site.
¡P
Haul roads should be sufficiently dampened to minimize fugitive
dust generation.
¡P
Wheel washing facilities should be properly maintained and
reviewed to ensure properly functioning.
¡P
Temporary exposed slopes and open stockpiles should be properly
covered.
¡P
Enclosure should be erected for cement debagging, batching and
mixing operations.
¡P
Water spraying should be provided to suppress fugitive dust for
any dusty construction activity.
¡P
Regular review and provide maintenance to dust control measures
such as sprinkler system.
Construction Noise Impact
¡P
Quieter powered mechanical equipment should be used as far as
possible.
¡P
Noisy operations should be oriented to a direction away from
sensitive receivers as far as possible.
¡P
Proper and effective noise control measures for operating
equipment and machinery on-site should be provided, such as erection of movable
noise barriers or enclosure for noisy plants. Closely check and replace the
sound insulation materials regularly
¡P
Vessels and equipment operating should be checked regularly and
properly maintained.
¡P
Noise Emission Label (NEL) shall be affixed to the air compressor
and hand-held breaker operating within works area.
¡P
Acoustic decoupling measures should be properly implemented for
all existing and incoming construction vessels with continuous and regularly
checking to ensure effective implementation of acoustic decoupling measures.
Water Quality Impact
¡P
Regular review and maintenance of silt curtain systems, drainage
systems and desilting facilities in order to make sure they are functioning
effectively.
¡P
Construction of seawall should be completed as early as possible.
¡P
Regular inspect and review the loading process from barges to
avoid splashing of material.
¡P
Silt, debris and leaves accumulated at public drains, wheel
washing bays and perimeter u-channels and desilting facilities should be
cleaned up regularly.
¡P
Silty effluent should be treated/ desilted before discharged. Untreated
effluent should be prevented from entering public drain channel.
¡P
Proper drainage channels/bunds should be provided at the site
boundaries to collect/intercept the surface run-off from works areas.
¡P
Exposed slopes and stockpiles should be covered up properly during
rainstorm.
Chemical and Waste Management
¡P
All types of wastes, both on land and floating in the sea, should
be collected and sorted properly and disposed of timely and properly. They
should be properly stored in designated areas within works areas temporarily.
¡P
All chemical containers and oil drums should be properly stored
and labelled.
¡P
All plants and vehicles on site should be properly maintained to
prevent oil leakage.
¡P
All kinds of maintenance works should be carried out within
roofed, paved and confined areas.
¡P
All drain holes of the drip trays utilized within works areas
should be properly plugged to avoid any oil and chemical waste leakage.
¡P
Oil stains on soil surface and empty chemical containers should be
cleared and disposed of as chemical waste.
¡P
Regular review should be conducted for working barges and patrol
boats to ensure sufficient measures and spill control kits were provided on
working barges and patrol boats to avoid any spreading of leaked oil/chemicals.
Landscape and Visual Impact
¡P
All existing, retained/transplanted trees at the works areas
should be properly fenced off and regularly inspected.
¡P
Control night-time lighting and glare by hooding all lights.